"Evacuation of power from 50 MVA, 132/33 KV Magam Grid Stn. Const of 33 KV double circuit line from Magam Grid Stn upto R/Stn Magam. Reconductoring/upgradation of conductor size from R/Stn Magam upto village arwah tapping point."
"Evacuation of power from 50 MVA, 132/33 KV Magam Grid Stn. Const of 33 KV double circuit line from Magam Grid Stn upto R/Stn Magam. Reconductoring/upgradation of conductor size from R/Stn Magam upto village arwah tapping point."
LUPCODE
Name of the Project
District
Amount Approved in HPC
Current Physical Progress
LUP1362
Evacuation of power from 50 MVA, 132/33 KV Magam Grid Stn. Const of 33 KV double circuit line from Magam Grid Stn upto R/Stn Magam. Reconductoring/upgradation of conductor size from R/Stn Magam upto village arwah tapping point.
Budgam
0.80000 crore
60%
Images of the Languishing Project (Current Status)